Owner Kuwait Oil Company
Place KUVEYT
Dates 1991-1992

The project consisted of design, supply and construction of  8,000 m2 Central Supply Warehouse, lined with insulated wall and roof cladding panels. Works included; infrastructure, foundation and concrete works; supply and erection of pre-engineered structural steel; furnishing of; warehouse offices, employees amenities, pallet racking cross lake web cam systems, electrically operated roller shutter doors, hinge doors, fire rated and sliding doors, dock levelers, etc; design, installation and commissioning of complete electrical facilities for the warehouse; central A/C orbit web cam for offices and employees amenities. complete fire alarm and fire fighting systems such as: sprinkler system, smoke detectors, heat detectors,  break glass call points, fire alarms, fire extinguishers, hose reels, fire safety notices and also overhead cranes and Electrical substations.